2014-2015
Project Phase 1: Terms of Reference
- High level document
- Sets the stage for the EA
- Approved by the Minister of Environment and Climate
- Change on December 15, 2015
Public Consultation
- 2 Public Meetings
- 4 Stakeholder Committee Meetings
- Over 300 Comment Submissions
2016-2019
Project Phase 2: Environmental Assessment (EA)
- Fulfilled the Terms of Reference
- Evaluated Alternatives, Selected a Preferred Alternative and Evaluated Environmental Effects
- Approved by the Minister of Environment, Conservation
- and Parks on November 6, 2019
Public Consultation
- 3 Public Meetings
- 7 Stakeholder Committee Meetings
- More than 40 Public Engagement Events
- Public Review of Draft and Final EA
- Over 800 Comment Submissions
2020-2035 (WE ARE HERE)
Project Phase 3: Detailed Design and Construction
- West Segment Detailed Design Initiated in Fall 2020
- West Segment Construction Pending Confirmed Funding
- Central and East Segment Design and Construction
- Timelines to be Confirmed, Pending Funding
Public Consultation
- 2 Public Open Houses
-
- Brimley Road South Multi-Use Trail Project
- West Segment Shoreline and Multi-Use Trail Project
-
- Ongoing Discussions with Key Interest Groups at Design Milestones
- Ongoing Public Engagement