Status Update and Next Steps

Fall 2020

Start of detailed design for West Segment Shoreline and Multi-Use Trail Project

Spring 2021

Confirmation of the EA concept and completion of the draft 30% design stage

Summer 2021

Completion of field studies and initiation of physical modelling work in partnership with the National Research Council (NRC) of Canada

Winter 2021/2022

Completion of physical modelling work and refinement to design based on results

Summer/Fall 2022

Completion of draft 60% design stage

Winter 2022/2023

Completion of final 60% design stage

Spring 2023

West Segment Shoreline and Multi-Use Trail Public Open House

Summer 2023

Anticipated update on design and construction timelines for Brimley Road South Multi-Use Trail Project

Fall 2023

Completion of West Segment Shoreline and Multi-Use Trail design

TBD

Construction of West Segment Shoreline and Multi-Use Trail Project to be started after completion of the Brimley Road South Multi-Use Trail, pending confirmation of funding, construction phasing, methodologies and timelines